Jordan Lake hydro project produces electricty
March 22nd, 2012The Army Corps of Engineers says in an update of the hydro-electric power project at Jordan Lake that the first generator began commercial operation in January and the second unit should be online by early to mid-summer.
Jordan Hydro Limited, Inc., a private company, began constructing two generators at the Jordan Lake dam near Moncure in November 2010. The Corps of Engineers administers the B. Everett Jordan Dam and Reservoir, including a recreation area at the dam.
The combined Kaplan-style modular turbine generators are expected to produce about 16,900 megawatt hours of electricity per year, enough to supply approximately 1,700 homes, the Corps' news release says. The power is sold to Progress Energy and distributed to homes and businesses in the area.
The City of Raleigh is considering a similar project at Falls Lake Dam, which is also managed by the Corps of Engineers for flood control and public recreation.
About 76 percent of water passing through the Jordan Lake dam will be used to create power that is non-polluting and emits no carbon dioxide into the atmosphere, the Corps says.
The amount of water released from Jordan Lake will not change for the hydroelectricity project, and will remain based on factors such as inflow, downstream flood conditions, municipal water requirements and water quality.
"That was one of the big concerns of stakeholders," Jordan Dam Operations Manager Craig Shoe said. "We're not going to change anything operationally. Jordan Hydro only uses the water that we regularly release."
Jordan Hydro, a subsidiary of North Fork Electric, Inc., has more information and photos of the Jordan Lake construction project here.